Crews are working on sewer upgrades between 4th and 5th North along the west side of Main Street.

r

Expected Impacts:r• Southbound traffic is reduced to one lane between 4th and 5th North on Main Street during work hours for the week ahead.r• 5th North is closed at the west side of Main Street due to construction activity.r• Parking along Main Street is not available in areas where crews are working.

r

r

r

r

r

r

r

r

r

r

r

r

r

r

Project Overview

r

Sanitary Sewer Line Phase – Start April 11thrCrews will install new sewer lines between 1st & 2nd South, 4th & 5th North, 5th & 6th North, 6th & 7th North, and along 7th North from Main Street to 100 East.

r

UDOT Main Street Rehab Phase – Start May 9thr• Reconstruct existing pedestrian ramps from 3rd South to 10thr• Add second northbound right turn lane from Main Street to 10thr• Curb and gutter work at 10th North and Main Streetr• Replace storm drain between 8th and 9th North along northbound lanesr• Reconstruct driveway approaches between 5th and 6th Northr• Replace one and a half inches of asphalt from 3rd South to 10th NorthrWork consists of replacing one and a half inches of pavement from 10th North to 3rd South along Main Street, and the addition of a second northbound right turn lane at 10th North. In addition to replacing the roadway surface, crews will reconstruct existing pedestrian ramps throughout the project. Curb and gutter, storm drain and driveway approaches will be replaced or repaired at specific locations.

r

During this project on-street parking will be affected in the area(s) where crews are working. Access to businesses and residences will be maintained during business hours. There may be short delays when crews are removing or replacing pavement, or trenching in front of driveway approaches.

r

Nighttime workrIncludes: Sewer trenching, installing sewer lines and the milling operations to remove pavement during the road rehabilitation phase.

r

Daytime workrIncludes: Filling and covering trenches, utility work, work to pedestrian ramps and asphalt paving operations.

r

Schedule is subject to change due to weather or materials availability.

r

r

r

r

Chris Baird
Chris Bairdhttps://servedaily.com
Chris is a family man with a beautiful wife and four kids. Three Girls, One Boy. He enjoys playing basketball, being outdoors, and the old normal.

Submit News

Visit our Forms to submit a recipe, obituary, contact us, or submit news. 

Related news